Curtis Roach>
Senior Project Manager, Engineering and Public Works
Town of Stouffville
Phone: 905-640-1126 x4241
curtis.roach@townofws.ca
Phase 1 – Aurora Road (north side), from McMullen Drive to Ballantrae Gates Plaza
Phase 2 – Highway 48, from Ballantrae Gates Plaza to Ballantrae Common
The Town has awarded this construction tender to Aqua Tech Solutions, Inc. The work includes:
WSP Canada Inc. has been retained to provide site inspection services and construction administration services.
Any planned disruptions to driveway access or Town services will be communicated in advance. Please label your trash and recycling containers as the Contractor may be required to move these containers once work is underway. The Town is not responsible for damage or loss to privately-owned appurtenances located within the public road right-of-way. Please ensure that any such appurtenances are removed prior to construction.
The project team will confirm works and scheduling and will issue Construction Notice to residents.
Senior Project Manager, Engineering and Public Works
Town of Stouffville
Phone: 905-640-1126 x4241
curtis.roach@townofws.ca
Warranty in effect until 27 June 2027.
Tendering complete, September 2026.
Construction to be completed no later than November 30, 2026.
111 Sandiford Drive, Stouffville ON, CA
customer.service@townofws.ca
(905) 640-1900
Accessible formats available upon request. Contact 905-640-1900 or customer.service@townofws.ca for assistance.
© 2024 Town of Whitchurch-Stouffville | Privacy and Disclaimer